- Government estimate
- $1,600,000
- What the agency expected to pay
- Winning bid
- $1,382,450
- The amount awarded
- Difference from estimate
- $217,550 below
- Bids received
- 6
- Range of bids
- $1,382,450 to $1,538,900
- Lowest to highest price offered
- Awarded to
- Horizon Mechanical
- Award date
- Sep 4, 2026
The award came in $217,550 (14%) below the government estimate. The government estimate is what the agency expected the work to cost before it saw any bids.
About This Contract
The City of Westbridge is seeking a contractor to replace HVAC equipment at three fire stations. Work must be performed while the stations remain operational.
The City of Westbridge seeks proposals from qualified mechanical contractors to replace aging HVAC equipment at Fire Stations 2, 4, and 6. Work includes removal of existing rooftop units, installation of new high-efficiency equipment, controls integration, and commissioning. Stations must remain fully operational throughout construction.
Why This Vendor Was Selected
Horizon Mechanical received the highest overall evaluation score based on price, relevant experience, technical approach, project team, and proposed schedule.
How the Winner Was Chosen
These criteria and weights were published in the solicitation before any bid was opened. A weight is the maximum number of points a proposal can earn on that criterion.
| Criterion | Stage | Weight | Committee average |
|---|---|---|---|
| Price | Technical | 30 pts30% of total | 29 |
| Technical Approach | Technical | 25 pts25% of total | 23 |
| Relevant Experience | Technical | 20 pts20% of total | 19 |
| Project Team | Technical | 15 pts15% of total | 14 |
| Schedule | Technical | 10 pts10% of total | 9 |
| Total | 100 pts | 94 |
Bid tabulation
6 bids were received and opened. 1 bid was withdrawn before opening and is listed below. Responsive means the bid met the requirements the solicitation set out.
- Horizon Mechanical$1,382,450
Westbridge, OH
AwardedScore 94 - Atlas HVAC$1,409,220
Canton, OH
ResponsiveScore 91 - Redwood Mechanical$1,441,800
Akron, OH
ResponsiveScore 88 - Summit Building Systems$1,475,100
Cleveland, OH
ResponsiveScore 84 - Westbridge Facilities Group$1,521,400
Westbridge, OH
ResponsiveScore 81 - Copperfield Plumbing$1,538,900
Westbridge, OH
Non-Responsive Westbridge, OH
Withdrawn
Protests
Bid protests are part of the procurement record but this agency does not publish them on the portal. You can request them through a public records request.
Solicitation Documents
- FAC-26-104-RFP.pdfRFP · Jul 12, 2026
- FAC-26-104-Mechanical-Specifications.pdfSpecifications · Jul 12, 2026
- FAC-26-104-Sample-Contract.pdfSample Contract · Jul 12, 2026
- FAC-26-104-Insurance-Requirements.pdfInsurance · Jul 12, 2026
- FAC-26-104-Notice-of-Intent-to-Award.pdfAward · Aug 31, 2026
- FAC-26-104-Bid-Tabulation.pdfBid Tabulation · Sep 5, 2026
Procurement Timeline
Every stage this purchase passed through, from planning to the end of the contract.
Where this stands now: Completion. The contract is still running. It will be marked complete when it ends.
Planning
CompleteThe agency defined the need and prepared the solicitation.
Published
CompleteJul 12, 2026, 11:49 AM EDT
Posted publicly and open to any qualified company.
Questions
CompleteAug 1, 2026, 11:49 AM EDT
The question period closed. Answered questions stay published with the solicitation.
Addenda
CompleteAug 4, 2026, 11:49 AM EDT
2 addenda issued. An addendum is a written change to the solicitation that every bidder must follow.
Bid deadline
CompleteAug 11, 2026, 11:49 AM EDT
Bidding closed at this time. Late submissions cannot be accepted.
Bid opening
CompleteAug 11, 2026, 11:49 AM EDT
6 bids were received and opened electronically by Sarah Chen. Witnessed by Diane Foster, Senior Buyer; Marcus Webb, Facilities Project Manager.
Evaluation
CompleteEvaluation finished and the panel produced a recommendation.
Intent to award
CompleteThe agency published its intended awardee, so other bidders had notice before the contract was final.
Protest period
CompleteBidders had a set window to formally challenge the decision. No protest is published for this solicitation.
Award
CompleteSep 5, 2026, 11:49 AM EDT
The award was published after 6 bids were received and opened.
Contract
CompleteOctober 4, 2026
Contract C-26-0058 is in place at $1,382,450 and starts on this date.
Amendments
CompleteSeptember 16, 2026
1 executed change took the contract from $1,382,450 to $1,411,200.
Completion
Happening nowJuly 21, 2027
The contract is still running. It will be marked complete when it ends.