- Government estimate
- $1,000,000
- What the agency expected to pay
- Winning bid
- $890,000
- The amount awarded
- Difference from estimate
- $110,000 below
- Bids received
- 6
- Range of bids
- $890,000 to $1,090,000
- Lowest to highest price offered
- Awarded to
- Lakeshore Roofing
- Award date
- Mar 8, 2026
The award came in $110,000 (11%) below the government estimate. The government estimate is what the agency expected the work to cost before it saw any bids.
About This Contract
Tear-off and replacement of the 68,000 sq ft membrane roof at the Westbridge Community Center, including insulation upgrades and lightning protection.
Why This Vendor Was Selected
Lakeshore Roofing submitted the lowest responsive, responsible bid.
Bid tabulation
All bids as opened and recorded by the Procurement Office. Responsive means the bid met the requirements the solicitation set out.
- Lakeshore Roofing$890,000
Mentor, OH
Awarded - Summit Building Systems$940,000
Cleveland, OH
Responsive - Riverstone Concrete$972,000
Canton, OH
Responsive - Redwood Mechanical$1,010,000
Akron, OH
Responsive - Westbridge Facilities Group$1,055,000
Westbridge, OH
Responsive - Copperfield Plumbing$1,090,000
Westbridge, OH
Responsive
Protests
Bid protests are part of the procurement record but this agency does not publish them on the portal. You can request them through a public records request.
Solicitation Documents
- PARKS-25-188-IFB.pdfIFB · Dec 9, 2025
- PARKS-25-188-Bid-Tabulation.pdfBid Tabulation · Feb 27, 2026
Procurement Timeline
Every stage this purchase passed through, from planning to the end of the contract.
Where this stands now: Every stage of this procurement is complete.
Planning
CompleteThe agency defined the need and prepared the solicitation.
Published
CompleteDec 9, 2025, 10:49 AM EST
Posted publicly and open to any qualified company.
Questions
CompleteJan 8, 2026, 10:49 AM EST
The question period closed. Answered questions stay published with the solicitation.
Addenda
CompleteNo addenda were issued. The solicitation was not changed after it was posted.
Bid deadline
CompleteJan 18, 2026, 10:49 AM EST
Bidding closed at this time. Late submissions cannot be accepted.
Bid opening
CompleteJan 18, 2026, 10:49 AM EST
6 bids were received and opened electronically by Sarah Chen. Witnessed by Diane Foster, Senior Buyer; Marcus Webb, Facilities Project Manager.
Evaluation
CompleteEvaluation finished and the panel produced a recommendation.
Intent to award
CompleteThe agency published its intended awardee, so other bidders had notice before the contract was final.
Protest period
CompleteBidders had a set window to formally challenge the decision. No protest is published for this solicitation.
Award
CompleteMar 11, 2026, 11:49 AM EDT
The award was published after 6 bids were received and opened.
Contract
CompleteMarch 28, 2026
Contract C-25-0107 started at $890,000.
Amendments
CompleteApril 27, 2026
1 executed change took the contract from $890,000 to $918,500.
Completion
CompleteAugust 15, 2026
The contract has ended. Its full record stays published.